TODOs
Phase 1: Setup - Production Infrastructure Deployment
- Objective: Lay the foundation for Hoop.dev by setting up the production environment.
- Checklist:
- Deploy containers, ingress, and set up persistent storage.
- Integrate with Active Directory/Single Sign-On (SSO).
- Requirements:
- Cloud provider access for Postgres deployment.
- Kubernetes access.
- Active Directory management access.
- Timeline: 1-2 weeks
- Who's Responsible: DevOps Team
Phase 2: Preparation - User, Connection, and Policy Configuration in Hoop.dev
- Objective: Get Hoop.dev ready for users by defining connections, teams, and policies.
- Checklist:
- Confirm Phase 1 is complete.
- Define the connections and establish the teams that will use Hoop.dev.
- Assign and set up User Groups within Hoop.dev.
- Implement policies to:
- Specify which users have access to certain resources.
- Determine who approves connections or executions.
- Requirements:
- Admin-level access to Hoop.dev.
- Credentials for connections.
- Azure AD group management access.
- Timeline: 1 week
- Who's Responsible: Admin Team and IT Security
Phase 3: Rollout - Onboarding & Training for Hoop.dev
- Objective: Ensure internal teams are comfortable and efficient using Hoop.dev.
- Checklist:
- Confirm Phase 2 is complete.
- Create 'how-to' guides for transitioning existing workflows to Hoop.dev.
- Onboard the first team and collect feedback.
- Roll out training webinars as necessary.
- Host Q&A sessions for clarity.
- Requirements:
- Established Hoop.dev policies.
- Admin-level access to Hoop.dev for training leads.
- Timeline: 2-3 weeks
- Who's Responsible: Training Team and First Adopter Team
Timeline
Pilot Phase (6 Weeks Total)
- Phase 1: Setup (Week 1)
- Deploying containers, setting up ingress, and persistent storage in the QA environment.
- Integration with Active Directory/SSO.
- Responsible: DevOps Team
- Phase 2: Preparation (Week 2)
- Defining connections, establishing teams, and setting up user groups in the QA environment.
- Implementing initial policies in Hoop.dev.
- Responsible: Admin Team and IT Security
- Phase 3: Rollout (Week 3)
- Onboarding and training for a limited number of users.
- Creating 'how-to' guides and hosting Q&A sessions.
- Responsible: Training Team and First Adopter Team
- Testing (Weeks 4-6)
- Extensive testing of the solution in the QA environment.
- Collecting feedback and making necessary adjustments.
- Responsible: QA Team and Feedback Collectors
Production Rollout (12 Weeks Total)
- Phase 1: Setup (Weeks 1-2)
- Production infrastructure deployment similar to the pilot but on a larger scale.
- Responsible: DevOps Team
- Phase 2: Preparation (Weeks 3-4)
- Configuration of users, connections, and policies in Hoop.dev for production use.
- Responsible: Admin Team and IT Security
- Integration with Customer Self-Service Platform (Weeks 5-12)
- Integrating the solution with the customer’s self-service platform.
- Enabling developers to start using the solution independently.
- Responsible: Integration Team and Developer Relations